High Bank Creek Restoration

Project Timeline

High Bank Creek has a long and interesting history. Here is a quick look at some of the major events on High Bank Creek and Barry Conservation District restoration efforts.

dam old1940s and earlier
The project site featured a dam and an operating grist mill in the town of Morgan.

1960s
The family of current landowner knocked down the former dam’s cement abutment as a safety precaution. Remnants of the walls remained in the creek, causing changes to the creek’s natural structure and function.

dam pre construction2 1991
A DNR electrofishing study of High Bank Creek confirmed the presence of 25 fish species, including brown bullhead and grass pickerel, but indicated that fish abundance among all species was low and that brown trout recruitment was also low.
1998
An unpublished DNR survey of the creek reported only 15 species. Among the absent species were brown bullhead and grass pickerel.
2008
A DEQ Biological Survey rated High Bank Creek at Bivens Road excellent for macroinvertebrate community.

2011
Major flooding caused massive bank erosion- widths of 2’-5’ at 2’-3’ depths- in the unstable channel above the Morgan Dam.
High Banks Bridge

 

 

2013
The 8’ Lawrence Rd culvert was replaced by a 35’ bridge which allows the stream to flow at bankfull width. Project partners: MDOT, BCRC, USFWS.

2014
The remnants of the Morgan Dam were removed (USFWS grant). Two perched and undersized culverts along the creek were replaced with appropriately-sized culverts (MDNR grant).

IMG_0825

2015
1200’ of streambank was restored along the creek with funding from MDNR. Substrate, macroinvertebrate, and fish passage studies were conducted.
2016
REad Final planting was done on the High Bank Creek restoration site.

The High Bank Creek Restoration Project was featured in some articles, check it out!

  • Restoration Project on High Bank Creek Benefits Local Community While Educating Students: Adapted from an article in the Hastings Reminder, September 19, 2016

While the efforts on High Bank Creek aimed to naturalize its structure and flow as well as improve wildlife habitat, the project also provided an enriching opportunity to research the impacts of conservation practices on stream ecology.

Grand Valley State University (GVSU) undergraduate students Olivia Cooley and Nick Preville received funding through the Pierce Cedar Creek Institute (PCCI) Undergraduate Research Grants for the Environment program to spend the summer collecting and analyzing fish and macroinvertebrate data from High Banks Creek.

Michigan DNR crew, along with GVSU students and BCD staff, capture and mark fish along the creek to monitor improvements in fish passage before and after the project.
Michigan DNR crew, along with GVSU students and BCD staff, capture and mark fish along the creek to monitor improvements in fish passage before and after the project.

Preville, a 2013 graduate of Bath High School, commented on how beneficial the field experience was for professional development.

“Getting to know other researchers and industry professionals is going to be huge going forward. The connections I made and the experiences I gained will really help when it comes time to apply for jobs.”
Cooley, a 2013 graduate of Thornapple-Kellogg High School agrees, “It was really great to get experience in the real world doing something that is actually important. In college, you mainly just sit in lectures…and this summer I was doing stuff that was real and meant something.”

Although construction was completed in September 2015, BCD will continue to partner with GVSU professor Dr. Eric Snyder and his students to monitor the creek for several years.